Re: Indirect labor

$
0
0

Hi Kamal Sir

 

...option 1. If you want to show this cost separately as indirect OH cost like Prod Mgmt cost, QC cost, Admn cost and Maint cost then create 4 CCtr as Prod Mgmt OH, QC oh etc and plan in KP06 and finally allocate these cost to prod deptt through assessment cycle. In CCS also create 4 separate attributes and assign relevant CE to identify in prod cost

 

In the above option how the cost will be charged to the production? I believe through separate activity types, Right? If yes then those activities are also to be included in routings.

 

Regards

 

Rajneesh