Re: Cannot Dispatch production Orders in CM25

$
0
0

Dear Mr. Brahmankar,

We set Adjust Dates to Adjust basic dates as you suggested.

We also had to set Scheduling control for detailed scheduling>Start is the past to 10 days.

This is because the first operation in a midpoint scheduled order will always occur before the operation being midpoint scheduled.

Thank you very much for your help.

Best regards,

Marc Richardson